Power Station Drainage Systems
Manby Transformer Station - Drainage System Investigation and Conceptual Design
Toronto, Ontario
- evaluation of existing drainage conditions at a 13 ha transmission station runoff quality and quantity monitoring and evaluation of results
- hydrologic model calibration based on monitoring results
- development of a conceptual plan for drainage improvements
Wiltshire Transformer Station - Drainage System Investigation and Conceptual Design
Toronto, Ontario
- evaluation of existing drainage conditions at a 1.5 ha transmission station
- development of a conceptual plan for drainage improvements
- development of proposed solution for oil spill containment and oil/water separation
|